|
CCCL
Articles
Featured Article,
January 2009
Canadian
National Railway Co. v.
Royal and Sun
Alliance Insurance Co. of Canada,
2008 SCC 66

© 2008
Rick H. Shaban and Sharon C.
Vogel
Full-text:
http://www.canlii.org/en/ca/scc/doc/2008/2008scc66/2008scc66.html
On November 21, 2008, the
Supreme Court of Canada found in favour of Canadian National
Railway Company (CNR), allowing CNR’s appeal, and set aside the
judgment of the Ontario Court of Appeal, restoring the trial
judgment in CNR’s favour, including interest and costs, of
approximately $40 million.
This case involved an action commenced by
CNR against the subscribing
Insurers under a Builders’ Risk Policy. The Policy was issued
in connection with the construction of CNR’s new larger diameter
tunnel constructed adjacent to an existing tunnel under the St.
Clair River between Port Huron, Michigan and Sarnia, Ontario.
The claim arose out of the
failure of a soft ground earth pressure balance tunnel boring
machine (“TBM”) which had been purchased by CNR to be used in
the construction of the tunnel. The Policy insured CNR against
“all risks of direct physical loss or damage ... to ...
all real and personal property of every kind and quality
including but not limited to the tunnel boring machine...and
structures, temporary works and underground tunnels in the
course of construction.” The
Policy, like most standard industry forms, contained an
exclusion for “the cost of making good…faulty or improper
design.”
At trial, considerable
evidence was led by CNR about the TBM, a complex machine. It
was, at the time, the largest TBM in the world and was the key
piece of equipment for the project. Lovat Inc., a Canadian
company, one of five world leading TBM manufacturers, was
selected as the TBM manufacturer. In addition, a significant
number of the world’s leading experts participated in the design
of the TBM, which was an exhaustive and sophisticated process.
There was no evidence at trial of any short cuts taken to save
costs in the design. To the contrary, considerable resources
were brought to bear to produce a state of the art machine.
Approximately two months into
tunnelling, the TBM failed because of a failure of the sealing
system caused by excess differential deflection (adjacent
components moving towards or away from each other beyond
acceptable tolerances). The Project was delayed for 229 days.
CNR made a claim on the Policy and the Insurers relied on,
inter alia, the faulty or improper design exclusion to deny
coverage. At trial, after 19 days of evidence and the benefit
of hearing considerable expert evidence, Ground J. concluded
that the Insurers had not proven that there was any fault in the
design of the TBM and that, therefore, the Insurers had failed
to satisfy their onus to establish the applicability of the
faulty or improper design exclusion.
The expert called by the
Insurers at trial had no TBM or tunnelling expertise. The trial
judge preferred the evidence of CNR’s expert, Dr. Les Hampson,
who did have such expertise, in finding that the failure of the
TBM was not foreseeable and therefore the faulty or improper
design exclusion did not apply. In reaching this conclusion,
Ground J. applied the foreseeability standard test as enunciated
in Foundation Co. of Canada v. American Home Assurance Co.
(1995), 25 O.R. (3d) 36 (Gen. Div.), aff’d [1997] O.J. No. 2332
(C.A.), i.e. the Insurer had the onus to prove that all
foreseeable risks had not been taken into account in the design
of the subject property for the “faulty or improper design”
exclusion to apply.
On Appeal, the majority of
the Court of Appeal modified the foreseeability test by:
1. Requiring not only that
all foreseeable risks must be taken into account in
the design but also that the design succeed in
accommodating those risks (a standard of perfection);
and
2. Failing to consider the
essential comparative component of the foreseeability test
(i.e. comparing the design in question to some standard).
The majority of the Court of
Appeal effectively applied a prima facie or perfection
standard, as enunciated in the Australian case of Queensland
Government Railways v. Manufacturer’s Mutual Insurance
(1968), [1969] 1 Lloyd’s L.R. 214 (H.C.A.), in finding that the
faulty or improper design exclusion applied to excuse the
Insurers from liability. In effect, the majority of the Court
of Appeal concluded that because the TBM failed, its
design was therefore faulty. This results-focussed test is, of
course, tautological. This approach rendered coverage under the
Policy illusory as every breakdown of a piece of equipment or
structure on a construction project would theoretically attract
the applicability of the exclusion. Importantly, adopting a
prima facie test would also effectively negate the onus on
an insurer to prove the exclusion as the failure itself would be
establish the exclusion without any other proof required by the
Insurer.
The Supreme Court of Canada
rejected the application of a prima facie test, instead
adopting a “state of the art” standard. Binnie J., in writing
for the majority, stated as follows:
“In my view, the “all risks” policy
afforded the CNR greater protection than that which the
majority in the Court of Appeal was prepared to allow. At
the time of contracting, all parties realized that this was
to be the largest earth-balance TBM ever built. Leading
experts were enlisted to provide what was described as a
“state-of-the art machine” (Exhibit 6, vol. 4, p. 742). The
“all risk” policy was written to cover physical damage to an
innovative piece of equipment almost the length of a
football field operating on a scale with which the state of
the art had no previous experience. The policy did not
exclude all loss attributable to “the design”, but only loss
attributable to a “faulty or improper design”. The design
exhausted the state of the art but left a residual risk.
Failure is not the same thing as fault or impropriety. In my
view, the insurers did not meet the onus of bringing the
loss within the exclusion. I would allow the appeal. (para.
5)”
In reviewing the decision of the Court of Appeal, Binnie J.
noted that the trial judge held that “the TBM must be
designed to withstand all foreseeable risks” (emphasis
added), while the majority judgment of the Court of Appeal held
that the design must, in fact, and with the benefit of
hindsight, be shown to have succeeded in withstanding all
foreseeable risks. The majority of the Supreme Court disagreed
with the Court of Appeal, noting the conclusion of CNR’s expert,
Dr. Hampson, who wrote:
“[It] is not realistic to suggest
that all potential problems can and always should be
identified nor that the issues spotlighted by hindsight
should always have been picked out. Dr. Becker [the
Insurers’ expert] offers no evidence that the engineering
approach from Lovat was not rigorous apart from the somewhat
tautological contention that because a failure occurred they
should have avoided it ...
There are undoubtedly failures due
to incompetence, ignorance, complacency, blind faith,
mistakes and incorrect information. But there are also
failures of components that could not have been foreseen and
would not be focused on from the basis of information that
was available at the time -- it is my contention that the
St. Clair TBM is in this category. The value of hindsight
after a problem cannot be over-emphasized -- but this is far
removed from foreseeability in the real world.”
Binnie J. interpreted these
passages, stating as follows:
“I interpret these passages as
saying that at any given time risks may be foreseeable but
that in addressing those risks in an innovative project
there is inevitably a gap between the then current state of
the engineering art and omniscience, i.e. a state of perfect
knowledge and technique. This gap conceals risks within
risks that are not foreseeable on “the basis of information
that was available at the time . . . in the real world”. As
Lang J.A. pointed out, quite reasonably I believe, a design
is not “faulty or improper” simply because it falls short of
perfection in relation to all foreseeable risks (para.
194).”
After a careful review of the
applicable caselaw, including the Queensland case, the
Foundation case,
and Algonquin Power (Long Sault) Partnership v. Chubb
Insurance Co. of Canada (2003),
50 C.C.L.I. (3d) 107 (Ont. S.C.J.)
the majority of the Supreme Court held that the standard to be
applied is the “state of the art” standard, stating as follows:
“I do not believe that where, as
here, the risk is broadly defined (“metal deflects under
stress”), and the design addresses that risk with state of
the art diligence and expertise (as here), the insurers are
entitled to the exclusion just because, with the benefit of
hindsight, it turns out that “engineering knowledge and
practice lacked a proper appreciation” (to quote Queensland
again) of the design problem. A narrower interpretation of
the exclusion, it seems to me, best accords with the
intentions of the parties based on the plain meaning of the
words used, namely “faulty or improper”. If the insurers
wished to negotiate an exclusion of costs associated with
simple “design failure” or “design failure in conditions of
foreseeable risk”, it was open to them to have tried to do
so but that is not the wording of the policy and this
exclusion clause should not, in my opinion, be given that
effect. (para. 56)”
In applying the facts to the law, the Supreme Court of Canada
found that the trial judge’s conclusions were not tainted with
palpable and overriding error. The trial judge understood that
while differential deflection was a known risk in the design of
the TBM sealing system, the risk had been properly explored in
the design phase and, based on the existing state of the art, it
was not foreseeable that excess differential deflection was even
a remote or unlikely risk with this design and in these
circumstances. None of the experts involved in the Project, who
had substantial experience in the design and manufacture of TBMs
and with tunnelling projects, expressed any concern with respect
to differential deflection adversely affecting the sealing
system. Binnie J. stated that “the trial judge’s point, as I
understand it, was reminiscent of Sherlock Holmes: the
significance of the evidence was that the watchdogs did not
bark.”
The majority of the Supreme Court therefore restored the trial
judgment.
Richard H. Shaban, Guy J. Pratte and Sharon C. Vogel of the
Toronto offices of Borden Ladner Gervais LLP were counsel for
the successful Appellant at the Supreme Court of Canada.
Article
Archive
>> |