|
CCCL
Articles
Featured Article,
January 2010
Maystar General Contractors Inc. v. Newmarket
(Town), 2009 ONCA 675

© 2009 Matthew R. Alter
Full-text:
Click here or case name above
ONTARIO COURT OF APPEAL
RE-AFFIRMS THAT THE
INTEGRITY
OF THE TENDER PROCESS
IS ESSENTIAL TO FOSTER
FAIR AND ORDERLY BIDDING
Maystar General Contractors Inc. v. Newmarket
(Town), 2009 ONCA 675
In a decision
released September 24, 2009, on an appeal heard March 24, 2009,
the Ontario Court of Appeal unanimously dismissed the Town of
Newmarket’s appeal from the decision of Justice Laurence
Pattillo dated May 6, 2008 [reported in L.U.C. #75]. The
application judge found the Town to be in breach of contract
with Maystar for accepting the non-compliant bid of Bondfield
Construction Company Inc. for the construction of a recreation
centre.
The central
issues on this appeal were:
1.
Did the application judge err in law by failing to apply
the principles in the Ontario Court of Appeal’s decision in
Bradscot (MCL) Ltd. v. Hamilton-Wentworth Catholic District
School Board (1999), 42 O.R. (3d) 723 (C.A.) and by
distinguishing the case on the facts?
2.
Did the Town’s tender documents allow it to accept
Bondfield’s bid?
3.
Did the application judge err by finding that a
discrepancy in price necessarily rendered Bondfield’s bid
non-compliant?
4.
Was the Town entitled to accept a non-compliant bid and
did the Town’s Instructions to Bidders prevent Maystar from
suing the Town?
Issue 1: The
applicability of the Bradscot decision
Madam Justice
Feldman, writing for the Court of Appeal, agreed with the
application judge that the Bradscot case was
distinguishable on its facts from the circumstances in this
case.
Specifically,
the Court found that Bondfield’s bid price was uncertain and
therefore incapable of forming the basis of a contract. The
stipulated price in Bondfield’s bid, as set out in words and in
numbers, was $33,000,528. However, the GST amount was stated as
$2,346,960, which was not 7% of $33,000,528, but 7% of $33,528,000.
Further, the stated total cost of the work figure (for
stipulated price plus GST) was $33,874,960, which was the GST
sum of $2,346,960 plus $33,528,000. The Court found that in
this case it was unclear whether Bondfield intended the
stipulated price to be as stated, or to be what the stipulated
price would be working back from the total cost of work and GST
values.
The Court
further agreed with the application judge that, in this tender,
unlike the tender at issue in Bradscot, the GST and total
cost of work amounts were neither superfluous nor subordinate to
the stipulated price, but were an important component of the
Bondfield tender. Further, upon examining the provisions in the
Town’s Instructions to Bidders, the Court of Appeal concluded
that “[t]hese articles suggest that it is the stipulated price
rather than the total bid price that is the superfluous figure”.
The Court also
accepted Maystar’s argument and the application judge’s finding
that the nature of Bondfield’s error was similar to the error at
issue in the Ontario Court of Appeal’s decision in
Ottawa (City) Non-Profit Housing Corp. v. Canvar Construction
(1991) Inc. (2000),
3 C.L.R. (3d) 55. Although the Canvar case involved a
low bidder defending a damages claim on the grounds of a
mistaken bid, the Court, in that case, found that when Canvar’s
tender form and accompanying bid bond prices were read together
it was unclear which amount was the intended bid price.
The Court
further agreed with the application judge’s finding that the
Town had clearly corrected the Bondfield Bid, stating:
“[The Town] chose to view the stipulated price as the
price intended by Bondfield rather than the total cost amount,
then corrected the G.S.T. calculation and the total cost amount
to conform with its choice.” (paragraph 34)
Finally, the
Court found that the application judge was entitled to draw the
inference that, in making the contract award, Town Council had
considered a letter sent to the Town by Bondfield 5 days after
the opening of tenders, which purported to explain the
discrepancy between the stipulated price and G.S.T. and asked
the Town to accept its bid based on the lower of these values.
A copy of Bondfield’s letter was included in a report submitted
by Town staff to Town Council before the contract award, in
support of Town staff's recommendation to award the contract to
Bondfield.
The Court of
Appeal acknowledged that the Town was in a difficult situation
and may have believed that it was acting in good faith, but
stated as follows:
“. . . the Supreme Court has made it clear in the
cases it has decided that the integrity of the tender process is
essential in order to foster a fair and orderly bidding process
where contractors will expend the time, effort and expense to
bid, knowing they will be treated fairly and equally. A public
owner cannot undermine that process by purporting to accept a
bid with an uncertain price, or to encourage contractors to
believe that they can communicate with owners after the fact to
clarify or explain inconsistencies in their bids. In M.J.B.
Enterprises, at para. 54, Iacobucci J. pointed out that good
faith on the part of the owner is not a defence to a claim for
breach of contract.”(paragraph 38)
Issue 2: Did the Town’s tender
documents allow it to accept Bondfield’s bid?
The Town sought
to rely on provisions in the Instructions to Bidders, which
allowed it to check arithmetic extensions to ensure they were
correct, consider the bidder’s intent, waive any discrepancies,
errors or other defects in the bid form, and accept an
unbalanced, irregular or informal bid. The Court of Appeal
rejected this submission finding that the application judge had
properly considered the effect of the specific provisions of the
tender documents and had “...concluded that the discrepancy and
consequent uncertainty in the bid price submitted by Bondfield
constituted a fundamental error that was not able to be
unilaterally corrected or waived using any of the provisions of
the Instructions to Bidders”.
Issue 3: Did the application judge err by finding that a
discrepancy in price necessarily rendered Bondfield’s bid
non-compliant?
The Town
submitted that the application judge erred by treating the price
discrepancy as an automatic non-compliant bid and argued that
the discrepancy in the presentation of the price figures in the
Bondfield bid did not materially affect the price and gave
Bondfield no unfair advantage within the tender process. The
Court of Appeal found there to be no merit to this submission,
stating:
“The reason the price was materially affected in this
case, unlike in Bradscot, was because there was
uncertainty as to which price was the intended bid price until
the correction was made. That after the fact correction gave
Bondfield an unfair advantage over other bidders and was not
compliant with the terms of the tender documents.” (paragraph
44).
Issue 4: Was the Town entitled to accept a non-compliant bid
and did the Town’s Instructions to Bidders prevent Maystar from
suing the Town?
The Town’s final
argument was that it was entitled to rely upon the privilege
clause in its Instructions to Bidders to accept Bondfield’s bid
as “unbalanced, irregular or informal” without any breach of its
Contract A with Maystar.
The Court of
Appeal dismissed this argument, agreeing with the application
judge that the language of the articles relied upon did not
clearly entitle the Town to accept a non-compliant bid. The
Court also distinguished the Town’s privilege clause from the
one at issue in
Tercon Contractors Ltd. v. British Columbia (Minister of
Transportation and Highways), [2008] 2 W.W.R. 410,
finding that it was not as broad as the Tercon clause and
did not specifically allow the owner to accept a non-compliant
bid.
© 2009
Matthew R. Alter
Article
Archive
>> |