|
CCCL
Articles
Featured Article,
June 2008
Nav Canada v. Greater Fredericton
Airport Authority Inc., 2008 NBCA 28

© 2008 T.
Arthur Barry, Q.C.,
Stewart McKelvey
The decision of the New Brunswick
Court of Appeal in Nav Canada released on March 20, 2008
settled a $223,000 dispute between Nav Canada and GFAA over who
should pay for some new navigation equipment installed in the
course of a runway extension project (subject of course to
potential appeal to the Supreme Court of Canada.) Nav Canada
ended up with the bill. The resolution of the dispute by the
Court of Appeal has provided a potentially significant
“incremental” change in the common law, one which is of note for
construction lawyers.
In a nutshell,
it has long been held that the performance of a pre-existing
obligation would not qualify as fresh or valid consideration to
vary an existing contract: Stilk v. Myrik
(1809), 2 Camp. 317, 170 E.R. 1168. The rule in
Stilk required that fresh
consideration be a condition precedent to the enforceability of
any contract variation. In reasons which thoroughly analyze the
common law history of the doctrine requiring fresh
consideration, Robertson, J.A. held:
[7] … I conclude that the
arbitrator erred in finding that the variation was supported by
fresh consideration. As a matter of law, however, I am prepared
to recognize and adopt an “incremental” change in the
traditional rules by holding that a variation unsupported by
consideration remains enforceable provided it was not procured
under economic duress.
Nav Canada and
GFAA were parties to an Aviation Services Facilities Agreement
("ASF Agreement") which included terms governing responsibility
for certain capital expenditures. As part of the $6,000,000
runway extension project, GFAA requested that Nav Canada
relocate an instrument landing system to the runway being
extended. Rather than relocate existing equipment, Nav Canada
concluded that it made better economic sense to replace the
navigational aid with another type labelled a distance measuring
equipment or a "DME". It was GFAA’s position that Nav Canada
should pay the acquisition costs of $223,000 for the DME. In a
letter to the Authority, Nav Canada stated that it would not
provide for the purchase of the DME in its fiscal budget unless
GFAA agreed to pay the acquisition cost. Justice Robertson held
that the practical effect of that letter was to force GFAA to
pay, in light of the fact that GFAA had already expended $6
million, and Nav Canada’s refusal amounted to a threat to hold
up the use of the extended runway for at least another year.
GFAA wrote to
Nav Canada on February 20, 2003, indicating it would pay, but
“under protest”. On the basis of that letter, Nav Canada
completed the work, and incurred the $223,000 expense. GFAA
refused to pay.
The dispute
was referred to arbitration. The arbitrator held that there was
nothing in the ASF Agreement entitling Nav Canada to claim
reimbursement for the costs of acquiring the DME. However, the
arbitrator held that the subsequent exchange of correspondence
between the parties gave rise to a separate and binding contract
that was supported by consideration, and that Nav Canada was
entitled to recover the acquisition costs on that basis. The
arbitrator rejected the argument that the words "under protest"
were sufficient to negate contractual liability.
The decision
was appealed to the Court of Queen's Bench, where it was set
aside. The appeal judge found that the "under protest" letter
could not be interpreted as giving rise to a separate agreement
that the Airport Authority would pay for the DME, but rather
that the Airport Authority would pay only if it were found to be
contractually responsible under the ASF Agreement. The appeal
judge held that Nav Canada was not entitled to reimbursement for
the cost of the navigational aid.
The Court of
Appeal characterized GFAA’s “under protest” letter promising to
pay for the DME as a variation to the existing contract. That
is, the finding of the arbitrator that there was no obligation
on GFAA to pay for the DME was correct. “In short, Nav Canada
promised nothing in return for the Airport Authority’s promise
to pay for a navigational aid that it was not contractually
bound to pay for under the ASF Agreement.” (para. 19).
Robertson, J.A. found that the arbitrator had erred in finding
that the variation was supported by fresh consideration (and
constituted therefore a binding agreement). Thus, if the
traditional rule requiring consideration applied, the GFAA
promise to pay was not binding. The Court of Appeal took the
opportunity, however, to examine in detail whether the
traditional rule requiring consideration should provide the
answer, or whether there was good reason to move away from the
strict application of the rule. Robertson, J.A. offered several
reasons for doing so:
1. the doctrine in Stilk
v. Myrick was an unsatisfactory way of addressing the
enforceability of post-contractual modifications. “…The
reality is that existing contracts are frequently varied and
modified by tacit agreement in order to respond to contingencies
not anticipated or identified at the time the initial contract
was negotiated. As a matter of commercial efficacy, it becomes
necessary at times to adjust the parties’ respective contractual
obligations and the law must then protect their legitimate
expectations that the modifications or variations will be
adhered to and regarded as enforceable.”;
2. the Courts should openly
recognize that while some gratuitous promises are not bargains
supported by consideration, there may be other sound reasons for
enforcement. “…the consideration doctrine and
the doctrine of promissory estoppel work in tandem to impose an
injustice on those promisees who have acted in good faith and to
their detriment in relying on the enforceability of the
contractual modification.” (para. 29); and
3. “…the
doctrine… developed centuries before the recognition of the
modern and evolving doctrine of economic duress. The doctrine of
consideration and the concept of bargain and exchange should not
be frozen in time so as to reflect only the commercial realities
of another era. If the courts are willing to formulate and adopt
new contractual doctrines, they are equally capable of modifying
the old. To the extent that the old doctrines interfere with the
policy objectives underscoring the new, change is warranted.” (para.
30).
Thus, the
Court accepted that a post-contractual modification, unsupported
by consideration, may be enforceable as long as it is
established that the variation was not procured by economic
duress. This latter condition is of particular note in the
construction field, where pressure can be exerted to secure
agreement to changes in many contexts. Robertson, J.A. sets out
a thorough review of the developing doctrine of economic duress
and held at paragraph 55 that:
“It is a central feature of the
doctrine that a plea of economic duress will fail unless is it
established that the promisor (victim) had no practical
alterative but to capitulate to the demands of the promisee
(coercer). …If the evidence establishes that other practical
alternatives were available to the victim, the plea of economic
duress must fail at the threshold stage. On the other hand, if
the evidence establishes a lack of practical alternatives, the
law requires the analysis to continue before a finding of
economic duress is warranted. In short, the absence of practical
alternatives is evidence of a lack of consent, but is not
conclusive of the issue. The law is still concerned with the
possibility that the contractual variation may have been
consented to for reasons that the promisor alone deems
sufficient. This leads us to ask how one goes about assessing
the presence or absence of “consent”
The Court
found that in the circumstances of the case, GFAA had no
practical alternatives. Nav Canada had exerted pressure to
obtain what amounted to a contractual modification of the ASF
Agreement. It was held that GFAA did not consent to the
variation irrespective of the circumstances. In that regard,
the Court noted both the “under protest” language and the
absence of any evidence that GFAA otherwise acquiesced.
Article
Archive
>> |