|
CCCL
Articles
Featured Article,
June 2009
Hub Excavating Ltd. v. Orca Estates Ltd.
2009 BCCA 167
© 2009 Jason S. Twa and John S. Logan

John S. Logan
Full-text:
Click here or case name above
The Nature and Scope of an Owner’s Duty of Fairness:
Hub Excavating Ltd. v. Orca Estates Ltd.
In 2007, the British Columbia Supreme Court in handing down its
decision in Hub Excavating Ltd. v. Orca Estates Ltd.
[supplementary reasons for judgment -
2008 BCSC 21 (CanLII)] arguably expanded the nature and
scope of the duty of fairness owed by an owner to bidders in the
tender process. That decision, however, was appealed by the
owner and on April 17, 2009, the British Columbia Court of
Appeal allowed the appeal and overturned the trial judge’s
decision. In its decision, the Court of Appeal clarified the
nature and scope of an owner’s duty of fairness in the tender
process.
The Facts
In this case, the owner had, over a period of years, developed
several phases of a residential development project. In 2002,
the owner had considered proceeding with “Phase 12” of the
project but decided to defer it in favour of proceeding with a
different phase that was considered more profitable after the
owner had received a written estimate from its engineer
estimating construction costs for Phase 12 at $825,000.00. One
of the issues with Phase 12 was uncertainty about the amount of
rock that needed to be removed and the cost of doing so.
In 2004, the owner again considered options for proceeding with
Phase 12. The owner’s engineer provided an oral estimate of
construction costs for Phase 12 of $600,000 or $650,000. Based
on this estimate, the owner proceeded with putting Phase 12 out
to tender and tender documents were sent out to invited bidders
in April 2004. The tender documents contemplated a lump sum
price and included a privilege clause which provided that the
owner was not obliged to accept any of the tenders. In
addition, the tender documents provided for a 60 day
irrevocability period which was later reduced by an addendum to
30 days.
Shortly after putting Phase 12 out for tender, the owner’s
engineer revised his estimate of construction costs for Phase
12, increasing the estimate to $950,000 with a note stating, “I
knew I should never have given you a guess cost the other day.
I was way out”. At trial, the engineer stated that he must have
been “brain dead” when he gave the original estimate of
$650,000.
After receiving the revised estimate, the owner continued with
the tender process, deciding to wait to see what the bids came
in at, still hopeful that the tender would result in good prices
being received. Upon the tender closing on May 21, 2004, the
low bidder’s price was $1,080,914.
Upon all the tenders being received, the engineer advised the
contractor that its bid was “close to the engineer’s estimate”
and that he would advise the owner of the bids and would get
back to the contractor “as soon as he got the go ahead”. The
contractor took this to mean that the owner would be proceeding
with the project promptly and would award the contractor the
job.
Shortly after the closing of the tender, the owner reviewed the
bids and decided not to proceed with the project as the prices
received were too high. The owner, however, failed to advise
the contractor, Hub Excavating Ltd., or other bidders of its
decision until the expiry of the irrevocability period.
The contractor, having learned that its bid was close to the
engineer’s revised estimate of $950,000, commenced an action
against the owner alleging negligent misrepresentation and that
the owner had breached its duty of fairness by using the bidding
process to obtain market information with no intention of
proceeding with the project.
Lower Court Decision -
2007 BCSC 1512 (CanLII)
While the trial judge accepted that the owner’s decision not to
proceed with the project was made for valid economic reasons,
the British Columbia Superior Court focused on the owner’s
decision to put the project out for tender in the first place.
There was no suggestion by the trial judge that the owner did
not intend to proceed with the project if the bids came in at
the range of the engineer’s original oral estimate of $650,000,
rather, he found that the owner had no “bona fide belief”
or “realistic expectation” that the price would come in at or
under the oral estimate and had treated the contractor with
“callous indifference”. The trial judge did not hesitate to
review the reasonableness of the owner’s business decision to
proceed to tender and held that the owner had no reasonable
expectation of the bids being near the oral estimate and, as a
result, the owner was in breach of its duty of fairness.
The Court’s reasoning at trial arguably expanded the nature and
scope of an owner’s duty of fairness. Perhaps the most
significant potential expansion to the duty of fairness was the
Court’s general comment that the duty of fairness could arise
even before a contractor has submitted a bid, in this case being
the owner’s decision to proceed to tender. This represented a
significant extension to the duty of fairness from previous case
law and raised the question as to how an owner could be subject
to a contractual duty when the contract creating that duty,
being Contract A which arises upon a compliant bid being
submitted, has not yet arisen.
At trial, the Court held that the owner breached its duty of
fairness in three ways:
(1) In proceeding with a futile bidding process when it knew
or ought to have known from the outset that the project was not
economically feasible;
(2) By the owner’s engineer making inaccurate statements
that led the contractor to believe it would be awarded the job;
and
(3) In failing to advise the contractor promptly of its
decision not to proceed with Phase 12.
Decision of the BC Court of Appeal
The owner appealed the trial decision and the British Columbia
Court of Appeal allowed the appeal, holding that the trial judge
had mischaracterized the nature and scope of the implied duty of
fairness.
First, the Court of Appeal held that the trial judge erred in
finding that the duty of fairness arose before the formation of
Contract A. The Court of Appeal, relying on their earlier
decision in Midwest Management (1987) Ltd./Monad Contractors
Ltd. v. BC Gas Utility Ltd., stated that there is no
free-standing duty of fairness in the bidding process
independent of the contractual duty of fairness.
Second, and perhaps more importantly, the Court of Appeal held
that the duty of fairness is procedural in nature. That is, the
duty of fairness is “an obligation to treat all bidders fairly
and equally in the process of assessing the bids” and does not
extend to other aspects of the tendering process.
While the contractor argued that the Courts ought to scrutinize
an owner’s decision to proceed with a futile tender call on the
basis that such conduct strikes at the heart of the integrity of
the tender process, the Court of Appeal disagreed. The Court
affirmed an owner’s entitlement to make its own business
judgments, refusing to substitute its view of what makes
business sense for that of the owner, stating:
“…Questions such as whether to go to tender, or whether it is
economically feasible to proceed with a project with any of the
bids submitted, are discretionary business judgments. Unless
the owner has breached a contractual term, the court should be
loathe to express its views on such matters…”
The Court of Appeal noted that the judicial scrutiny the
contractor called for would create uncertainty for owners as to
what pre-bid investigation and economic certainty would be
required in order to avoid liability before going to tender.
In the present case, there was significant uncertainty about the
amount of rock on site and cost of removal of the rock which
presented challenges as to whether the project was economically
feasible. The owner had decided to “test the waters” by putting
the project out to tender stipulating a lump sum contract. The
tender documents made it clear to the bidders that the owner was
not obliged to accept any bids. While noting that the
engineer’s estimate of $600,000 to $650,000 was “clearly
unrealistic”, the Court of Appeal held that the answer was not
judicial intervention to second guess the owner’s business
decision to go to tender on the basis that it was a breach of
the contractual duty of fairness as the duty does not extend
that far. Instead, in an approach reminiscent of the Court of
Appeal’s decision in Tercon Contractors Ltd. v. British
Columbia (Transportation and Highways), the Court looked to
industry response to curb such behaviour, noting that any
perceived unfairness in the owner’s conduct will be felt by the
owner in damages to its reputation and its future opportunities
in its business community.
The Court of Appeal also held that the alleged misrepresentation
by the owner’s engineer could not support an allegation of a
breach of the contractual duty of fairness as it did not produce
unequal or inconsistent treatment in the bid process. The
misrepresentation did not affect how bids were assessed or the
owner’s decision not to proceed with the project. As such, the
misrepresentation was only relevant to the contractor’s claim
for negligent misrepresentation.
With respect to the trial judge’s findings that the owner
breached the duty of fairness in failing to promptly advise the
contractor of its decision not to proceed with the project, the
Court of Appeal held that the trial judge had ignored that the
tender documents provided for a 30 day irrevocability period and
that the implied duty of fairness could not override that
express contractual term.
© Jason S. Twa and John S. Logan of Jenkins Marzban Logan LLP
Article
Archive
>> |