|
CCCL
Articles
Featured Article,
March 2010
Tercon Contractors Ltd.
v. British Columbia
(Transportation
and Highways),
2010 SCC 4
© 2010
Bruce Reynolds and Sharon Vogel
For the full-text of the decision cited in this case comment:
Click here
For a PDF version of this case comment:
Click here
Case Comment:
Tercon Contractors Ltd. v. British Columbia: the Final Nail
in the Coffin of the Doctrine of Fundamental Breach?
The Supreme Court of Canada released its
reasons in the much anticipated decision in
Tercon Contractors Ltd. v. British Columbia (Transportation and
Highways),
2010 SCC 4 on February 12,
2010. In a five/four decision, the majority found in favour of
Tercon, allowing the appeal. The Court agreed on the
appropriate framework of the analysis as to the enforceability
of the exclusion clause in issue, but were divided on the
applicability of the relevant exclusion clause to the facts at
hand.
The facts of Tercon arose out of a
tendering contract between Tercon Constructors Ltd. ("Tercon")
and Her Majesty the Queen in Right of the Province of British
Columbia (the "Province') which issued the tender call. The key
issue in the case was the interpretation of provisions in the
contract relating to the eligibility to bid and a damages waiver
which excluded compensation resulting from participation in the
tendering process.
In 2000, the Ministry of Transportation
and Highways for the Province issued a request for expressions
of interest ("RFEI") for designing and building a highway in
northwestern British Columbia. Six teams made submissions,
including Tercon and Brentwood Enterprises Ltd. ("Brentwood").
Later in 2000, the Province informed the six proponents that it
now intended to design the highway itself and would issue a
request for proposal ("RFP"), which RFP in fact was issued on
January 15, 2001. Under the terms of the RFP, only the
six original proponents were eligible to submit a proposal. The
RFP also included an exclusion clause which stated as follows:
2.10 … Except as expressly and specifically permitted in
these Instructions to Proponents, no Proponent shall have any
claim for compensation of any kind whatsoever, as a result of
participating in this RFP, and by submitting a Proposal each
Proponent shall be deemed to have agreed that it has no claim.
[Emphasis added] (para. 61)
Subsequent to the issuance of the RFP,
Brentwood teamed up with Emil Anderson Construction Co. ("EAC")
because it was unable to submit a competitive bid on its own.
EAC was not one of the six qualified bidders. Together,
Brentwood and EAC submitted a bid in Brentwood's name.
Brentwood and Tercon were the two short-listed proponents. The
Province ultimately selected Brentwood as the preferred
proponent.
Tercon brought an action seeking damages,
alleging that the Province had considered and accepted an
ineligible bid and that, but for that breach, Tercon would have
been awarded the contract. The trial judge agreed and awarded
approximately $3.5 million in damages and pre-judgment interest
to Tercon.
The Court of Appeal reversed the trial
judge’s decision. Tercon sought and obtained leave to appeal to
the Supreme Court of Canada.
Was the Brentwood Bid
Ineligible?
The trial judge had found that the
Brentwood bid was in substance, although not in form, from a
joint venture of Brentwood and EAC and that it was, therefore,
an ineligible bid. The British Columbia Court of Appeal
concluded that it was unnecessary to address this issue.
The Province had submitted: (1) that a
joint venture is not a legal person and that therefore the
Province could not and did not contract with a joint venture;
and (2) that the Province did not award the contract to EAC and
EAC had no contractual responsibility to the Province for
failure to perform the contract. These two arguments were not
accepted by the Supreme Court. The majority noted that the
issue was not, as these arguments assumed, whether the Province
contracted with a joint venture or whether EAC had contractual
obligations to the Province. The issue was whether the Province
considered an ineligible bid.
The Province also took the position that
there was no need to look beyond the face of the bid to
determine who was bidding, arguing that the proposal was in the
name of Brentwood and that therefore the bid was from a
compliant bidder. The majority found that the trial judge, in
rejecting this position, had made no error. Justice Cromwell
stated that the trial judge's finding that the Brentwood bid was
in fact on behalf of a joint venture was unassailable.
The Province's third argument was that
there was no term in the RFP that restricted the right of
proponents to enter into joint venture agreements with others;
this arrangement left Brentwood, the original proponent, in
place and allowed it to enhance its ability to perform the
work. This submission was also rejected by the Supreme Court.
The majority found that, when read as a whole, the provisions of
the RFP did not permit the addition of a new entity, as occurred
here. Furthermore, the Court noted that the Province never gave
a written decision to permit this change as required by the RFP.
Both the majority and minority found no
fault with the trial judge's conclusion that the bid was in fact
submitted on the behalf of a joint venture of Brentwood and EAC
which was an ineligible bidder under the terms of the RFP. The
acceptance of Brentwood's bid breached not only the express
eligibility provisions of the tender documents but also the
implied duty to act fairly towards all bidders.
Was the Exclusion Clause
Enforceable?
The Court then turned to consider the
exclusion clause at issue. The consideration of the
applicability of the exclusion clause is the most interesting
element of the decision and will have far reaching implications
for the tendering process and the construction industry in the
future.
Both the majority and the dissenting
Justices agreed that the doctrine of fundamental breach should
be retired in respect of the enforceability of exclusion
clauses. Justice Binnie, writing for the minority, stated "[o]n
this occasion we should again attempt to shut the coffin on the
jargon associated with 'fundamental breach' Categorizing a
contract breach as 'fundamental' or 'immense' or 'colossal' is
not particularly helpful."
In the
result, Justice Binnie stated that the test as to the
enforceability of an exclusion clause is comprised of three
stages, pursuant to which the court asks itself:
1.
Whether, as a matter of interpretation, the exclusion
clause even applies to the circumstances established in
evidence. This will depend on the Court’s assessment of the
intention of the parties as expressed in the contract.
2. If
the exclusion clause applies, whether the exclusion clause was
unconscionable at the time the contract was made, “as might
arise from situations of unequal bargaining power between the
parties” (Hunter Engineering Co. v. Syncrude Canada Ltd.,
[1989] 1 S.C.R. 426, at p. 462).
3. Whether
the Court should nevertheless refuse to enforce the valid
exclusion clause because of the existence of an overriding
public policy, proof of which lies on the party seeking to avoid
enforcement of the clause, that outweighs the very strong public
interest in the enforcement of contracts.
Justice Cromwell, for the majority,
agreed with the above three-stage test.
The Majority's Application of the Test
to the Facts
The majority of the Supreme Court
concluded that the exclusion clause did not cover the Province's
breaches based on the facts before it. The majority found that
the RFP process put in place by the Province was premised on a
closed list of six bidders, and that, therefore, a contest with
an ineligible bidder was not part of the RFP process and was, in
fact, expressly precluded by its terms. The majority held that
the "very premise of its own RFP process was missing" and that
the work was awarded to a party that could not be a participant
in the RFP process. Therefore, it was found that Tercon's claim
was not barred by the exclusion clause because the clause only
applied to claims arising "as a result of participating in [the]
RFP" and not to claims resulting from the participation of
other, ineligible parties. Furthermore, the words of the
exclusion clause were found to be "not effective to limit
liability for breach of the Province's duty of fairness to
bidders."
The majority rejected the Province's
argument about the commercial sophistication of Tercon, noting
that this argument had two weaknesses:
1. It
assumed the answer to the real question before the Court which
was: What does the exclusion clause mean? The consequences of
agreeing to the exclusion clause depend on its construction.
2. The
Province overlooked its own commercial sophistication and the
fact that sophisticated parties can draft very clear exclusion
and limitation clauses.
The majority contrasted the exclusion
clause at issue in the case before it with the limitation clause
at issue in Guarantee Company of North America v. Gordon
Capital Corp. [1999] 3 S.C.R. 423 (“Gordon Capital”),
which provided that legal proceedings for the recovery of "any
loss hereunder shall not be brought … after the expiry of 24
months from the discovery of such loss." The Court found this
language found in a fidelity bond to be clear. The Court used
the Gordon Capital case as an example which demonstrated
that sophisticated parties are capable of drafting clear and
comprehensive exclusion provisions.
The majority concluded that in attempting
to determine whether or not an exclusion clause applies, a
significant issue to be considered will be whether or not the
defect in the tender calling authority’s conduct is “such that
it is completely outside … [the RFP] process.”
In reviewing the text of the exclusion
clause within the context of the RFP as a whole, the majority
found that it could not accept that the parties could have
intended to “exclude a damages claim resulting from the Province
unfairly permitting a bidder to participate who was not eligible
to do so” (para. 78).
The Minority's Application of the Test
to the Facts
In respect of applying the test to the
facts of the case, the minority disagreed with the majority,
finding that the exclusion clause did apply. In analysing the
exclusion clause, Binnie J. accepted “the trial judge’s view
that the Ministry was at fault in its performance of the RFP,
but the conclusion that the process thereby ceased to be the RFP
process appears to me, with due respect to colleagues of a
different view, to be a 'strained and artificial interpretatio[n]
in order, indirectly and obliquely, to avoid the impact of what
seems to them ex post facto to have been an unfair and
unreasonable clause'” (para. 128).
In commenting on the bargaining power of
the respective parties, Binnie J. referred to the fact that
Tercon was a major contractor and was “well able to look after
itself in a commercial context.” Justice Binnie suggested that
Tercon need not bid if it did not “like what [was]
proposed”(para. 131).
Justice Binnie concluded that there was
not any overriding public policy that would justify the Court's
refusal to enforce the exclusion clause.
Justice Binnie concluded that while the
Ministry's conduct was in breach of Contract A, that conduct was
not so extreme as to engage an overriding and paramount public
interest in curbing contractual abuse. It would appear that,
here, Binnie J. was making an oblique reference to non-compliant
bids. It remains to be seen whether or not the Tercon
case will, in fact, open the floodgates in tendering cases
involving non-complaint bids; however, inasmuch as no Contract A
can be formed by the submission of a non-compliant bid, the
issue is, in the result, arguable.
Conclusion
It is clear that the Tercon
decision will have a significant effect on the construction
industry and the tendering process in Canada. It is likely that
tender calling authorities will give further consideration to
drafting very carefully worded exclusion clauses. However, at
least in the case of government tendering authorities, regard
must be had to their obligation to draft such clauses such that
any applicable policy mandate to provide for a fair and
equitable tendering process is maintained.
© 2010
Bruce Reynolds and Sharon Vogel
Article
Archive
>> |