|
CCCL
Articles
Featured Article, May 2007
Double N Earthmovers Ltd. v. Edmonton
(City), 2007 SCC 3.
Jurisdiction: Alberta (Supreme Court of Canada)
Author: Jean C. van der Lee, Q.C. Field LLP
FACTS: The City of Edmonton put out a call
for tenders, a condition of which was that the equipment used
for the job be manufactured in 1980 or later. Sureway submitted
a tender, an item of which listed the equipment as manufactured
in 1980, but the serial number revealed 1979, and another
which contemplated the use of one of two rental units from
1979 and 1980. Double N submitted a tender, and was the next
lowest bidder, but Sureway's was selected. Some of the work
performed under Contract B made use of the pre-1980 equipment,
a condition the City purported to have waived. Double N had
informed the City that Sureway did not own any post 1980 equipment
prior to the acceptance of the tender. Double N sued the City
for breach of contract and for the profits it would have realized
had it been awarded the Contract. Double N claimed the city
had accepted a non-compliant bid, had breached their duty
to investigate Sureway's bid, engaged in bid shopping, awarded
the contract to Sureway on terms other that those set out
in the tender documents, and breached Contract A with Double
N by allowing Sureway to use pre-1980 equipment in performing
Contract B.
MAJORITY ANALYSIS: (LeBel, Deschamps, Fish,
Abella and Rothstein) The City did not accept a non-compliant
bid. While Sureway's tender suggested a 1979 rental unit,
the make and model and cost per hour listed by them with respect
to that item in the bid applied to the 1980 rental unit. The
City did not have a duty to investigate Sureway's bid; the
City had the right to inspect the bid but no duty to do so.
The City was not obligated to investigate the claims made
by Double N because that would encourage attacks by rival
bidders, frustrating the integrity of the bidding process.
In addition, there was no reason for parties to expect the
owner to investigate whether a bidder will comply, when each
bidder is legally obliged to comply in the event their bid
is accepted. The City did not engage in "bid shopping"
as a result of its pre-award negotiations with both Double
N and Sureway, since some measure of negotiation was anticipated
by this particular call for tenders (contrary to the situation
in MJB Enterprises). The contract was not awarded on terms
other than those contemplated by the tender documents, because
at the time the City accepted Sureway's bid, 1980 equipment
was what Sureway was obliged to supply. Even though the trial
judge found that Sureway had been deceitful, it was Sureway's
intention at the time the bid was accepted (to bid 1980 equipment
and subsequently convince the City to allow them to use 1979)
that was relevant. Also, the City was unaware of Sureway's
deceit until after the acceptance, evidencing the absence
of collusion between the City and Sureway to disregard the
tender terms. The City did not breach Contract A with Double
N (through the waiver of the pre-1980 equipment requirement
in Sureway's performance of the contract) because the waiver
was conduct which occurred after the award of Contract B.
Contract B is a distinct contract to which the unsuccessful
bidders are not privy, and thus obligations owed to unsuccessful
bidders are discharged by the time this contract (B) has been
formed. For policy reasons, parties to contract B should not
be subject to constant surveillance and scrutiny from the
unsuccessful bidders, as it would introduce an element of
uncertainty to Contract B.
DISSENT: (McLachlin, Bastarache, Binnie
and Charron) The trial judge concluded the age of the equipment
was an essential term of Contract A. Sureway's bid was non-compliant.
The City had an obligation to accept only compliant bids and
to treat all bidders fairly and equally, which was breached
by accepting Sureway's non-compliant bid. Owners have an obligation
to take reasonable steps to evaluate the terms of the bid
to ensure that they conform to the tender call. This obligation
requires that steps be taken to evaluate the bid for compliance
before acceptance. The City's casual approach to Sureway's
bid in light of the warning it had received from Double N
was unfair to other bidders. The bid purporting to supply
either 1977 or 1980 equipment was ambiguous at best and therefore
could not be considered compliant. The right to insist on
compliance cannot turn what is on its face a non-compliant
bid into a compliant one. Also, the integrity of the process
was not upheld by allowing a bidder to get rid of the competition
unfairly and then "hash it out" with the owner after
it has been awarded the contract. If what turned Sureway's
prima facie non compliant bid into a compliant one was the
City's right to insist on compliance, then the City was duty
bound to do that, at which they failed.
Article
Archive
>> |